Civil Construction

Ord Street subdivision

A 28 hectare site filled and levelled into a 29 lot subdivision, delivered ready for 48 homes in 22 weeks, on time and under budget.

Client
Newhaul Residential Pty Ltd
Capability
Civil Construction
Location
Geraldton WA
Completed
21 July 2025

RDH completed the Ord Street subdivision development in Geraldton, on time and under budget for our client Newhaul Residential Pty Ltd.

The 28 hectare (Ha) site was filled and levelled to create a 29 lot sub-division, complete with subdivisional roads, footpaths, retaining walls, bollards, street signs, a masonry acoustic wall, and all necessary underground services.

Scope of works included

  • Clearing and grubbing
  • Topsoil stripping
  • Fill importation, placement and compaction
  • Build subdivisional roads
  • Build footpaths
  • Build retaining walls
  • Install bollards and street signs
  • Install a masonry acoustic wall
  • Coordinate all necessary electrical, sewer, stormwater, and water in-ground services
Together with our sub-contractors, RDH delivered the Ord Estate ready for construction of 48 quality homes in 22 weeks.

More civil work

Related projects

Narngulu HMC storage pad extension
CivilFebruary 2026

Iluka Resources Limited

An extension to Iluka's Heavy Mineral Concentrate storage pad, built to support additional feedstock capacity at the Narngulu Mineral Separation Plant.

Riverina aerodrome earthworks
CivilJanuary 2026

Ora Banda Mining

A full airstrip build to support the rapid development of the Riverina Underground Mine and enable FIFO operations for site personnel.

Narngulu temporary grain storage earthworks
CivilDecember 2025

CBH Group

Peak Planning bulkheads built to meet the 2025/26 Harvest Program, covering bulk earthworks, drainage, pavement and hardstand works.

Have something similar to price?

Send through the scope and we will get back to you with a programme and a price.